Qwuloolt Estuary Restoration
 


HOME



ABOUT US



QWULOOLT ESTUARY



RESTORATION PLAN



 DOCUMENTS



PARTNERS

 

 

 

 

link to Tulalip Tribes link to City of Marysville link to Washington DOE link to NRCS Link to US FWS link to NOAA

Restoration Plan

Goals

The goal of the Qwuloolt Project is to restore historic tidal circulation and other natural processes and functions to the site. 

Project objectives established by the partners include:

  • Create a self-sustaining project requiring minimal construction and maintenance
  • Create a physical, chemical, and biological template on the site that allows natural processes to occur and critical functions to improve
  • Promote natural channel formation
  • Create areas for the development of diverse plant and forest communities
  • Facilitate the rate of recovery and revegetation of native species
  • Maintain migratory pathways for existing fish populations
  • Maximize cover, forage, and other habitat functions for fish
  • Balance public access and aesthetic considerations with ecological objectives

-- GO TO TOP --

Plan

Approach

The overall approach of the Qwuloolt Project is to create a cost effective, self-sustaining, and resilient estuary system on site that requires minimal construction and maintenance and allows natural processes to occur and critical functions to improve over time.

More specifically, restoring the Qwuloolt will involve restoring stream channels and typical site relief on the site, constructing setback levees to protect neighboring properties within the floodplain, planting native vegetation to promote habitat recovery, and removing four tide gates and levee sections along Ebey Slough to restore tidal connection with the broader Snohomish River estuary system. 

Restoration Activities


Stream Restoration

The Qwuloolt project involves relocating one mile of stream channel in lower Allen Creek and Jones Creek to its historic alignment based on a 1938 aerial photo that depicts remnant channels.  The relocation of the channels will restore stream habitat quantity and quality. 

Site Relief

Material extracted during the stream relocation will be used to fill the current ditched channel and other drainage ditches as well as to create typical topographic relief on the site.  Filling low areas and adding site relief along the channel edges will promote the return of natural processes such as tidal channel formation and sheet flow exchange once tidal influence is restored.  These actions will create a physical foundation on the site that will allow natural processes to occur and critical functions to improve over time.

Native Plants

Riparian areas along the stream channels, slough, and perimeter of the project area will be planted with native vegetation to facilitate the rate of recovery of plant and forest communities.

Levee Setback and Removal

Interior setback levees will also be installed or upgraded to protect neighboring industrial, sewage treatment, and other infrastructure and property located in the floodplain. Once setback levees are constructed, levees along Ebey Slough will be removed.  As much of the levee as possible will be removed because experts recommend full levee removal to reestablish historic and natural tidal exchange.  

Levee removal will restore fish access to estuary and side channel habitats and re-establish historic tidal influences.  Levee removal will also allow fish to access Jones and Allen Creek stream systems.

The restoration of physical, chemical, and biological estuarine processes, such as tidal circulation, are essential to restoring a critical estuary system that will improve water quality, production and transport of plant material and nutrients, utilization by estuarine dependent species, and other ecological functions.

Site Plan

Over the past few years, project partners have worked cooperatively to develop a restoration plan for the Qwuloolt. In early 2006, partners held a public informational meeting and open house to solicit feedback from the community on several levee breach alternatives.  You can view restoration alternatives evaluated as part of this process, including trail and public access alignments, on the Maps & Documents page. Based on input from the community, planning partners selected a large levee breach alternative as the preferred alternative for further refinement.

Since 2006, project partners have worked to refine the preferred alternative to enhance ecological and biological objectives and to reduce overall project impacts and costs  In early 2009, with the engineering and design assistance of the U.S. Army Corps of Engineers, project partners completed the following design for the Qwuloolt:     

Design




Implementation

The Qwuloolt Project will be implemented in two phases:

        - Stream Restoration
                In 2007, one mile of stream channel in lower Allen and Jones Creeks was restored to its                         historic location and natural alignment.  The project involved excavating 5,000 feet of new                     channel and filling in the old ditched channels to ensure that the creeks functioned properly.                    Look at Photos.

        - Estuary Restoration
                This phase of the project aims to restore tidal connection and a functioning estuary system                     on the Qwuloolt.  It will include levee setback construction and levee removal activities.                          Designs for this phase are outlined below.  Construction is planned for 2012-2013.  

-- GO TO TOP --

Design

Stream Restoration

The stream restoration component of the Qwuloolt Project restored one mile of stream channel in lower Allen and Jones Creeks.  Ditched portions of the streams were realigned to their historic locations as seen in this 1938 aerial photo.  

Channel Designs

The project included excavating 5,000 feet of new stream channel within the project area. Some of the existing ditched channels were also filled to ensure that the creeks function properly.  The tide gates and levees on Ebey Slough at the mouths of Allen and Jones Creek were not altered.  The figures below illustrate the new stream channel alignments for Allen and Jones Creeks.

Allen Creek
The  work on Allen Creek involved excavating 1,400 feet of channel that will act as a backwater channel for the main stream channel.  It was connected to a remnant portion of the historic Allen Creek channel at the downstream end but was not connected to the main Allen Creek channel on the upstream end.  The existing Allen Creek channel was not altered.  

Jones Creek
The  work on Jones Creek required excavating 2,500 feet of stream channel in order to match historic stream channel meanders.  The new channel was connected to Jones Creek on the upstream and downstream ends.  A small tributary, approximately 1,300 feet in length, was also be excavated south of the main channel.  Existing ditched channels were filled to ensure that the creeks functioned properly.  

You can view Restoration Photos or Contact Us for more information. 


Estuary Restoration

The estuary restoration phase of the Qwuloolt Project will restore tidal processes and an estuarine marsh system to 340 acres of floodplain.  The following project elements will be implemented:

  • Removal of 1,800 linear feet of levee along Ebey Slough
  • Construction of setback levees (1,700 ft and 4,000 ft) and a 0.8 acre fill area to protect adjacent properties located in the floodplain
  • Construction of a 6 ½ acre water runoff storage basin
  • Filling ditches and excavating starter channels to facilitate tidal channel formation
  • Constructing small internal berms to increase habitat complexity and attenuate waves
  • Planting native trees and shrubs

Typical Setback Levee Design

For plan sheets see Designs.

-- GO TO TOP --

Timeline

Task

Preliminary Designs

Jan 2008

Community Meeting & Public Comment

Feb  - May 2009

Final Designs

May - June 2012

Construction of Protective Levees

Jul 2012 - Aug 2013

Tidal Restoration (Levee and Tide Gate Removal)

Sep 2013


-- GO TO TOP--

Estimated Cost

Restoration of the Qwuloolt, including Allen and Jones Creek stream and estuarine restoration activities, is expected to cost approximately $7 million.  This project is made possible through the cooperation and financial support of its many partners including tribal, local, county, state, and federal agencies as well as private individuals and organizations.

Grant assistance has come from:
    
        National Oceanic and Atmospheric Administration's Community-based Restoration Program
        National Oceanic and Atmospheric Administration's Open Rivers Initiative Program
        National Fish and Wildlife Foundation's Puget Sound Marine Conservation Program
        Natural Resource Conservation Service's Wetland Reserve Program

        Pacific Coast Joint Venture
        US Fish and Wildlife Service's National Coastal Wetlands Conservation Program   
        Washington Department of Fish and Wildlife's Estuary and Salmon Restoration Program
        Washington State's Acquatic Lands Enhancement Account   

        Washington State Recreation and Conservation Office
        Washington State's Salmon Recovery Funding Board
        

-- GO TO TOP --

 
Page last updatedFebruary 10, 2012
Home contact